Kajaki 2 hydroelectric plant

Da Afghanistan Breshna Sherkat [100%]

HydroOperational

A hydro project record in Afghanistan on Solandor, a free database of clean energy projects and the investors who fund them across the Gulf, South Asia and South East Asia. Browse the full catalogue.

Record prj_gem_g100000604480Unverified
Capacity
100 MW
Technology
Hydro
Stage
Operational
Country
Afghanistan
Location
Helmand Province32.323, 65.118
Developer
Da Afghanistan Breshna Sherkat [100%]
Annual output
not published
Capex
not published
Capital sought
not published
Source
Global Hydropower Tracker, Global Energy Monitor
Last checked
11 Sept 2026

Every field this catalogue holds for the record is listed, including the ones its source leaves empty. A blank is a gap in the published source, not a gap in the record.

Ours is a public-source record. Claim it to correct anything above. Free, and your contact details are never shown.

About this project

100 MW hydro facility at Helmand Province, Afghanistan currently operating. Owner: Da Afghanistan Breshna Sherkat [100%]. Start year: 2022. Compiled from the Global Energy Monitor tracker; financial terms are not published and must be obtained from the developer. [Published 12 Sep 2026 from the Global Hydropower Tracker, March 2026 release.]

Where this sits in the catalogue

By capacity this is the 3rd largest of the 10 hydro records we hold in Afghanistan. The country has 23 records in total across every technology. A further 1 catalogued project sits within 25 km of it. See every record in Afghanistan or find it on the map.

Investment readiness

What a financier can currently see about this project without asking a question. Not a view on the project itself.

No score is shown, because the public record carries too little to score one honestly. A low band here would describe what we do not know rather than anything about the project. The dimensions below are what the sources actually evidence, and the gaps are what a developer can close in a minute by claiming the record.

Offtake / PPANot stated
Site controlNot stated
Grid connectionNot stated
Financials & returnsReturns not yet modelled
DeveloperNot stated
Data completeness0/8 key inputs provided

To become bankable

  • Secure an offtake agreement (PPA) or named offtaker
  • Secure site control (ownership or lease)
  • Apply for grid connection / evacuation
  • Provide developer track record / prior projects
  • Add a CAPEX budget
  • Add an expected annual generation estimate

Climate impact

Clean generation displaces grid power at 0.50 tCO₂/MWh. Generation estimated from capacity.

CO₂ avoided / yr

175,200 t

Over project life

4,380k t

Homes powered / yr

100,114

We hold no contact route for this project

This record comes from a public dataset, and that dataset does not publish a way to reach the developer. You can still register interest and we will tell you if that changes, but we will not pretend an introduction is available today.

If this is your project, claim the record and investors can reach you directly.

Is this your project?

This record is drawn from a public source. Claim it to correct it, state whether it is raising, and choose whether investors may be introduced to you. Nothing is published until we have checked it, and your contact details are never shown.

If you would rather not be listed at all, email hello@solandor.co and we will remove the record. No account, no form, and we do not ask why.

Claim this project

Developer site: www.gem.wiki/Kajaki_2_hydroelectric_plant

The Capital Radar

Told when Kajaki 2 hydroelectric plant changes

The Capital Radar goes out when the record moves: stages that shift, figures that are corrected, records that are added or retired across Afghanistan. Every number traced to the public dataset it came from.

Free. One click to leave, and we never pass your address on.

Questions about Kajaki 2 hydroelectric plant

How big is Kajaki 2 hydroelectric plant?+

Kajaki 2 hydroelectric plant is recorded at 100 MW of hydro capacity in Helmand Province, Afghanistan. That figure is the one its source publishes, not an estimate by Solandor.

Where is Kajaki 2 hydroelectric plant?+

Kajaki 2 hydroelectric plant is in Helmand Province, Afghanistan, at 32.3226, 65.1184. The coordinates are published by the source, so the location on the map is the site itself rather than a town centre standing in for it.

Who is behind Kajaki 2 hydroelectric plant?+

The record names Da Afghanistan Breshna Sherkat [100%] as the developer of Kajaki 2 hydroelectric plant. That is what the published source says; Solandor holds no view on the ownership structure behind it and does not verify commercial control.

Is Kajaki 2 hydroelectric plant operating?+

Kajaki 2 hydroelectric plant is recorded at operational stage in Afghanistan. Stage comes from the source dataset and is re-checked against it; the page shows the date of the last check, so you can see how current that is.

Where does Solandor's information about Kajaki 2 hydroelectric plant come from?+

This record is drawn from Global Hydropower Tracker, Global Energy Monitor, published at https://globalenergymonitor.org/projects/global-hydropower-tracker/. Solandor is a free public catalogue of clean energy projects and their funders; every field it holds is shown, including the ones the source leaves empty. Tell us if anything is wrong and we will correct it, and if you are Kajaki 2 hydroelectric plant and would rather not be listed at all, say so and we will remove it.