Not yet built

The pipeline

1516 clean energy projects on record are not yet operating, 553,161 MW in total. That is more capacity than the 344,867 MW already running across 3661 operating projects. Every record names the public dataset it came from.

A pipeline is not a forecast. 97,755 MW of this is under construction and committed. The rest sits at earlier stages, where announcement and delivery are very different things. The ladder below is ordered by certainty, least to most.

By stage

Concept

1/4

234,820 MW

573 projects

Announced or at early study. No commitment implied.

Feasibility

2/4

1,600 MW

1 projects

Under formal study, ahead of a build decision.

Development

3/4

218,987 MW

620 projects

Permitting, land and offtake being assembled.

Construction

4/4

97,755 MW

322 projects

Committed and being built.

Where it is being built

MarketProjectsCapacity
India436212,964 MW
the Philippines401125,685 MW
Vietnam28745,018 MW
Pakistan5035,815 MW
Oman2535,472 MW
Nepal13331,491 MW
Indonesia10823,246 MW
Saudi Arabia1214,570 MW
Malaysia88,393 MW
the United Arab Emirates75,120 MW
Cambodia114,728 MW
Thailand163,165 MW

By technology

Wind249,558 MWHydro139,918 MWStorage122,005 MWSolar34,168 MWGeothermal4,764 MWBioenergy2,749 MW

Who is building it

Named developers only, by pipeline capacity on record. Many projects carry no developer in their source dataset and are not counted here.

DeveloperProjectsCapacity
Energy Development Oman SAOC [100%]1121,750 MW
National Hydroelectric Power CORP (NHPC) [100%]716,410 MW
Adani Green Energy [100%]1014,750 MW
Pakistan Water and Power Development Authority; China Three Gorges CORP (CTG)614,308 MW
Pakistan Water and Power Development Authority [100%]1012,738 MW
PT Kayan Hydro Energy [100%]610,375 MW
Energy Development Oman SAOC110,000 MW
NHPC Ltd [100%]99,855 MW
Greenko Energy Holdings [100%]59,260 MW
Torrent Power Ltd [100%]67,400 MW
Nepal Electricity Authority (NEA) [100%]196,800 MW
Ministry of Water Resources Government of India; Ministry of Energy Government of Nepal16,480 MW

Questions about the pipeline

How much clean energy capacity is under development in the region?+

Solandor holds 1516 clean energy projects that are not yet operating across the Gulf, South Asia and South East Asia, totalling 553,161 MW. That is 62% of all capacity on record. Of it, 97,755 MW is under construction, which is the portion with money committed.

Does a project in the pipeline mean it will be built?+

No. The stages differ enormously in certainty. A project at concept has been announced and may never proceed; one under construction is committed and being built. Solandor keeps them separate for that reason and never presents a combined figure as though it were built capacity.

Where does the pipeline data come from?+

Every record traces to a named public dataset or a source page for that project, listed on the sources page. Solandor compiles and attributes; it does not estimate capacity or invent stages. Browsing is free and no account is required.

The Capital Radar

Follow the pipeline as it moves.

The Capital Radar covers what was added, what changed stage and what was retired across the markets we track, with the source for each entry.